Background: The brief was that an infrastructure upgrade and the best outcome for handling the large stormwater drain that was traversing the site was required.
Strategy: Applicable requirements were obtained from Sydney Water via applications for servicing and adjustment.
Solution: To achieve this, the following pipe deviations were required. 225mm and 1200mm sewer deviations, plus the 200mm watermain amplification.